With only two weeks to the opening, there is a great deal happening every day. It was most rewarding to visit the site on 17th November and to see several milestones achieved. These included – the scaffolding now coming down rapidly – the connection of the mains electricity – the painting of the boat bay doors – the installation of all the windows – the completion of the balcony railings – the testing of the heating, toilets and showers.